



You are about to leave this page. Do you want to proceed?
House Construction The model units and 152 houses have been completed, while the construction of 29 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 48 units have been turned over. […]
HOUSE CONSTRUCTION 206 houses have been completed, while the construction of 27 house units are ongoing and in full swing.House Construction refers to the number of houses completed or under construction. SITE DEVELOPMENT Site Development is fully completed.Site Development covers site clearing, grading, roads, utilities, open parking, and related work. AMENITIES The Clubhouse, Pool, Playground, […]
House Construction The model units and 231 houses have been completed, while the construction of 43 house units are ongoing and in full swing. Site Development is fully completed Amenities The Clubhouse, Gate Guardhouse, Basketball Court, and Boulevard Landscape have been completed. The Pool and Playground are expected to be completed by Q4 2023. Turnover […]
We use cookies to improve your experience on https://ajoya.com.ph. Click “I accept” to let us know you’re okay with our cookie policy.