House Construction The model units and 152 houses have been completed, while the construction of 29 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 48 units have been turned over. […]
Site Development Site development is now at 73% with Phase 1A set to be finished by Q3 of this year. House Construction Construction of 40 new units are now in full swing.
House Construction The model units and 90 houses have been completed, while the construction of 121 house units are ongoing and in full swing. Site development is nearing completion at 99% Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse, and Boulevard Landscape have been completed. Turnovers 9 units have been turned over. Turnover Offices […]
TURNOVERS 22 house units have been turned over. HOUSE CONSTRUCTION 127 houses have been constructed along with the model units, while the construction of 40 house units are ongoing and in full swing. AMENITIES The gate, guardhouse, pool, clubhouse, boulevard landscape, and playground have been completed, while the basketball court is set to be completed […]
We use cookies to improve your experience on https://ajoya.com.ph. Click “I accept” to let us know you’re okay with our cookie policy.