House Construction The model units and 152 houses have been completed, while the construction of 29 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 48 units have been turned over. […]
Stay informed with the latest construction updates on Ajoya Capas. HOUSE CONSTRUCTION 223 houses have been completed, while the construction of 18 house units are ongoing and in full swing.House Construction refers to the number of houses completed or under construction. SITE DEVELOPMENT Site Development is fully completed.Site Development covers site clearing, grading, roads, utilities, […]
House Construction The model units and 159 houses have been completed, while the construction of 39 house units are ongoing and in full swing. Site Development is fully completed Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 61 units have been turned over. […]
Site Development Site development is now at 73% with Phase 1A set to be finished by Q3 of this year. House Construction Construction of 40 new units are now in full swing.
We use cookies to improve your experience on https://ajoya.com.ph. Click “I accept” to let us know you’re okay with our cookie policy.