House Construction The model units and 152 houses have been completed, while the construction of 29 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 48 units have been turned over. […]
TURNOVERS Property turnovers are set to commence in Q4 2022. Are you in search of funding for your Ajoya Property? Click here to learn more about our home loan options and services.
Stay informed with the latest construction updates on Ajoya Pampanga. HOUSE CONSTRUCTION 192 houses have been completed, while the construction of 102 house units are ongoing and in full swing.House Construction refers to the number of houses completed or under construction. SITE DEVELOPMENT Site Development is fully completed.Site Development covers site clearing, grading, roads, utilities, […]
HOUSE CONSTRUCTION 223 houses have been completed, while the construction of 18 house units are ongoing and in full swing.House Construction refers to the number of houses completed or under construction. SITE DEVELOPMENT Site Development is fully completed.Site Development covers site clearing, grading, roads, utilities, open parking, and related work. AMENITIES The Clubhouse, Pool, Playground, […]
We use cookies to improve your experience on https://ajoya.com.ph. Click “I accept” to let us know you’re okay with our cookie policy.