Construction Updates

Ajoya Pampanga Construction Updates Q3 2024

HOUSE CONSTRUCTION 180 houses have been completed, while the construction of 88 house units are ongoing and in full swing.House Construction refers to the number of houses completed or under construction. SITE DEVELOPMENT Site development is nearing completion at 99%.Site Development covers site clearing, grading, roads, utilities, open parking, and related work. AMENITIES The Clubhouse, […]

Construction Updates

Ajoya Pampanga Construction Updates Q1 2024

House Construction 124 houses have been completed, while the construction of 98 house units are ongoing and in full swing. Site development is nearing completion at 99% Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse, and Boulevard Landscape have been completed. The Town Plaza is set to be completed by Q4 2024. Turnovers 54 […]

Construction Updates

Ajoya Pampanga Construction Updates Q4 2023

House Construction The model units and 105 houses have been completed, while the construction of 112 house units are ongoing and in full swing. Site development is nearing completion at 99%. Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse, and Boulevard Landscape have been completed. Town Plaza is set to launch in Q1 2024. […]

Construction Updates

Ajoya Pampanga Construction Updates Q3 2023

House Construction The model units and 90 houses have been completed, while the construction of 121 house units are ongoing and in full swing. Site development is nearing completion at 99% Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse, and Boulevard Landscape have been completed. Turnovers 9 units have been turned over. Turnover Offices […]

Construction Updates

Ajoya Pampanga Construction Updates Q2 2023

House Construction 72 house units have been completed as well as the model units which have been launched. The construction of 130 house units are ongoing and in full swing. Site development is nearing completion at 99% Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse, and Boulevard Landscape have been completed. Turnovers 6 units […]

Construction Updates

Ajoya Pampanga Construction Updates Q1 2023

House Construction 55 house units have been completed as well as the model units which has been launched. The construction of 121 house units are ongoing and in full swing. Site development is nearing completion at 99%. Amenities The Clubhouse, Basketball Court, Pool, Playground, Gate Guardhouse and Boulevard Landscape have been completed. Turnovers 3 units […]

Construction Updates

Ajoya Pampanga Construction Updates Q4 2022

TURNOVERS Property turnovers are set to commence in Q1 2023. HOUSE CONSTRUCTION 55 house units have been constructed, while the construction of 107 house units are ongoing and in full swing.  AMENITIES The guardhouse and the boulevard landscape are completed. The clubhouse, basketball court, pool, and playground are set to be completed in Q1 2023. […]

01. Construction-Update-Ajoya-Cabanatuan-600x400
Construction Updates

Ajoya Cabanatuan Construction Updates Q4 2021

TURNOVERS First batch of property turnovers is set to commence in Q1 2022. Need assistance in funding your Ajoya Cabanatuan property? Read more about our home loan offerings and services through this LINK. HOUSE CONSTRUCTION Our Construction Team has completed 24 house units while 179 other units are under construction. AMENITIES The main amenities at Ajoya […]