House Construction The model units and 152 houses have been completed, while the construction of 29 house units are ongoing and in full swing. Site Development is fully completed. Amenities The amenities have been completed such as the clubhouse, pool, playground, basketball court, gate guardhouse, and boulevard landscape. Turnovers 48 units have been turned over. […]
TURNOVERS 3 house units have been turned over. HOUSE CONSTRUCTION 137 houses have been completed, while the construction of 100 house units are ongoing and in full swing. AMENITIES The guardhouse, gate, and boulevard landscape have been completed, while the basketball court and clubhouse are set to be completed by Q1 2023. SALES 100 units […]
Site Development Site development is now at 73% with Phase 1A set to be finished by Q3 of this year. House Construction Construction of 40 new units are now in full swing. The landscaping work along the Main Boulevard is set to be completed by December of this year while main amenities including Parks and Playground, Basketball Court, Swimming Pool, and Landscaping in other areas are expected by Q2 of 2022.
House Construction The model units and 188 houses have been completed, while the construction of 59 house units are ongoing and in full swing. Land Development is fully completed Amenities The Gate Guardhouse, Basketball Court, and Boulevard Landscape have been completed. The Clubhouse is set for completion by Q3 2023, while the Pool and Playground […]
We use cookies to improve your experience on https://ajoya.com.ph. Click “I accept” to let us know you’re okay with our cookie policy.